Munich, October 1 2026

Together with Stadtwerke Schweinfurt, we are building a battery energy storage system with around 20 MW of power and around 50 MWh of capacity at the Oberndorf substation. Commissioning is planned for Q1 2027.

Together with Stadtwerke Schweinfurt, we have reached an important milestone in the construction of the large-scale battery storage system in Schweinfurt-Oberndorf: the topping-out ceremony. Representatives from politics, public administration, business, academia and the energy sector joined the project team to celebrate the progress on site.

The project

The storage system is being built directly at the existing substation and will connect to the public grid through it. It has a power rating of around 20 megawatts and a capacity of around 50 megawatt-hours. As a stand-alone facility, it is not tied to any single wind or solar plant. It draws electricity from the grid and feeds it back at a later time. This adds flexibility to the power system, which becomes more important as the share of wind and solar generation grows.

A partnership on equal terms

enerpeak and Stadtwerke Schweinfurt are delivering the project together as project partners with WT Energiespeicher responsible for construction as EPC partner. We thank everyone involved: the Stadtwerke, WT Energiespeicher, the planning and construction companies, the authorities and the financing partners.

“With the large-scale battery storage system in Oberndorf, we are actively helping to shape tomorrow’s energy infrastructure. The project adds flexibility to the power system and expands our expertise in an important field of the future. Together with our partners, we are taking responsibility for a modern and future-proof energy supply in the region,” says Thomas Kästner, Managing Director of Stadtwerke Schweinfurt GmbH.

Next steps

The remaining construction phases will follow until commissioning in the first quarter of 2027. “Our shared goal is to advance the remaining project phases consistently and bring the facility into operation as planned,” says Dr. Stefan Seipl, enerpeak.

Project data

  • Project: Schweinfurt-Oberndorf battery storage
  • Location: Schweinfurt-Oberndorf, at the substation
  • Power: approx. 20 MW
  • Capacity: approx. 50 MWh
  • Planned commissioning: Q1 2027