Building Germany’s energy storage infrastructure together
enerpeak develops utility-scale battery storage in Germany, from site securing through permitting to turnkey operation. We collaborate with financing partners, co-developers, and strategic investors to jointly realize one of Europe’s largest infrastructure opportunities.

Battery Storage: The new infrastructure asset class of the energy transition
1.
Market demand
Germany needs at least 68 GW of controllable capacity by 2030, according to the official demand analysis by the Federal Network Agency. Battery storage is the fastest and most flexible technology to fill this gap. The annual installation requirement is over 5 GW, and the current expansion rate lags far behind. For investors, this means a structural demand surplus that will persist for years.
2.
Revenue models
Utility-scale battery storage generates revenue through several independent income sources: primary frequency control (FCR), automatic frequency restoration reserve (aFRR), intraday arbitrage, and prospectively other system services. This diversification of revenue streams reduces individual market risk and creates a robust return profile.
3.
Cost effectiveness
The system costs for lithium iron phosphate (LFP) batteries have fallen by over 50% in the last five years and are expected to continue declining. At the same time, revenue potentials are increasing due to higher volatility in electricity markets. The combination of decreasing investment costs and growing revenue opportunities continuously improves project economics.
Key figures
2 GW+
Pipeline with network reservations
10+
in planning nationwide
Up to 4 years
Typical development time until commissioning
Up to 380kV
Covered grid-levels
Selected projects
The following projects showcase our development capabilities across different stages and requirements, from successfully navigating complex permitting procedures, to strategic partnerships with municipal utilities, to developing ultra large scale storage systems. They are representative of our broader pipeline of roughly 2 GW: technically sound, coordinated early with all stakeholders, and consistently advanced through to construction readiness.

Planning resolution in the municipality of Künzing
- Federal State: Bavaria
- Power: >100 MW
- Grid level: High voltage (110 kV)
- Status: Ready to build
Highlight: Successful collaboration across two municipalities and districts to achieve planning resolution (Satzungsbeschluss).

Ultrahighvoltage project in the city of Münchberg
- Federal State: Bavaria
- Power: >300 MW
- Grid level: 380 kV
- Status: Planning
Highlight: Approved grid reservation by TSO.

Partnership project in the city of Schweinfurt
- Federal State: Bavaria
- Power: 20 MW
- Grid level: Mid voltage (20 kV)
- Status: Under Construction
Highlight: Parternship with utility of Schweinfurt (utility).

Midvoltage project in the city of Kappeln
- Federal State: Schleswig-Holstein
- Power: 10 MW
- Grid level: Mid-voltage (20 kV)
- Status: Planning
Highlight: Privileged permission §35 BauGB approved.
Why enerpeak
Pipeline with substance
Our development pipeline includes over 2 GW of battery storage projects at various stages of development. Each project undergoes a structured site review and feasibility analysis before being added to the pipeline.
Technical and commercial depth
Our team combines experience in the energy industry, project financing, grid planning, and plant construction. This combination enables us to fully manage projects internally, from site acquisition to commissioning, without reliance on external development partners for core processes.
Strategic supply chain partnerships
Through our partnership with system integrators for and producers of battery storage systems, inverters, and transformers, we have access to competitive system prices and secured supply capacity.
Integrated development approach
enerpeak covers the entire value chain: site security, permitting, grid connection planning, EPC management, and operations management. For investors, this means having a single point of contact throughout the entire project lifecycle with clear responsibilities and reduced interface risks.
Partnership models
We work with different partner structures that are tailored to the strategy and requirements of our investment partners. We define the specific collaboration individually. Contact us, and we will develop the appropriate structure together.
Co-Development
Joint project development from site security to construction maturity. You bring capital, network, or regional market knowledge, and we take care of the operational development. Risk and value creation are shared in partnership.
Project financing
Provision of equity or debt for projects in advanced development by partners. Structured financing with clearly defined return profiles, tailored to your risk/return requirements.
Asset acquisition
Acquisition of storage projects in development and ready for construction. For institutional investors looking to add fully developed infrastructure assets to their portfolio, with secured location, permits, and grid connection.
Let’s talk
Whether it’s co-development, project financing, or asset acquisition: we look forward to the conversation. Contact us for an initial confidential discussion about our pipeline and potential collaboration.
info@enerpeak.de
enerpeak GmbH
Oberanger 38
80331 München
Deutschland